The government has told Cambridge City Council not to grant permission for Christ's College's new library while it decides whether to call the scheme in.

The government has stopped Cambridge City Council from granting planning permission for Christ’s College’s new library, for now. Councillors approved the scheme a week ago.

The Planning Casework Unit at the Ministry of Housing, Communities and Local Government sent the council a holding direction dated 13 October. It tells the council “not to grant permission on this application without specific authorisation”. The letter is published on the council’s planning register for application 26/02109/FUL.

What the direction does

It is issued under Article 31 of the Development Management Procedure Order 2015. The letter says it gives the Secretary of State time to consider whether to “call in” the application under Section 77 of the Town and Country Planning Act 1990. If that happened, the decision would be taken by the Secretary of State instead of the council.

The letter makes three points about its own limits:

  • the council can still consider the application, form a view on it, or refuse it
  • it is “for procedural purposes” and is not “any indication of the Secretary of State’s attitude” towards the scheme
  • it was issued by officials under delegated powers

It does not say who asked for the scheme to be called in, or how long the decision will take. The council’s case officer acknowledged the letter on 14 October, according to the email chain filed on the same register.

Approved, but no permission yet

The city council’s planning committee voted for the scheme on 7 October. The college says the vote was six to one. Approval at committee is not the same as permission: that only exists once the council issues a decision notice. On 16 October the register still listed the application as “Awaiting decision”, with no notice issued.

So the college cannot yet rely on the second approval. Its statement after the vote said it would work through the planning conditions and “begin the next phase as soon as possible”, starting with a temporary kitchen and dining hall in Second Court.

The court case is separate

The college’s first permission, granted in November 2025 for an identical scheme, is under judicial review. The Christ’s Lane Action Group brought the challenge. The college’s statement says the High Court hearing is scheduled for 20 October.

The council and the college have already asked the court to quash that first permission by consent. The action group refused, because it wants a judge to rule on its arguments. The second application was meant to settle the matter. The holding direction means the second approval cannot become a permission until the government decides.

What it means for you

Nothing changes on Christ’s Lane yet. No building work can start on the strength of the new approval while the direction stands. The college’s existing library stays as it is.

If the Secretary of State calls the scheme in, the application will be decided nationally rather than by the city council. If not, the council can issue the permission councillors voted for. We will report the outcome, and what happens at the High Court on 20 October.

The full scheme, the objections and the four grounds of the legal challenge are in our report on the 7 October decision. Other schemes in the city are on our Cambridge planning news page.

Sources