Councillors voted 6-1 for Christ's College's new library on Christ's Lane. A High Court challenge to the first approval is still listed for 20 October.
Christ’s College has won planning permission for its new library for the second time in a year. The first approval is still being challenged in the High Court.
Updated 16 October: on 13 October the government issued a holding direction telling the council not to grant this permission while it decides whether to call the scheme in. Our report.
The city council’s planning committee approved the scheme on Wednesday 7 October. The council’s list of the day’s decisions records it as approved. The college says councillors voted six to one in favour.
The college will knock down its 1976 library, a two-storey building along Christ’s Lane, and replace it with a four-storey one. Christ’s Lane is the busy walkway between St Andrew’s Street and Drummer Street bus station.
Why the same plan went back to committee
The committee first approved an identical application on 29 October 2025, and the permission was issued on 7 November. The Christ’s Lane Action Group, a residents’ and objectors’ group, then applied for judicial review.
In March, Mr Justice Kimblin gave the group permission to argue all four of its grounds, calling them “strongly arguable”. That is set out in the officer report for this week’s meeting.
The group’s four grounds, as the report summarises them:
- the committee was misled about Historic England’s advice, which had found harm from the bulk of the building
- the report gave confusing advice on whether there was harm to listed buildings at all
- councillors were wrongly told the scheme would secure the listed building’s “optimum viable use”
- councillors were not told about less harmful alternatives, including schemes approved on the site in 2011 and 2016
The council and the college then asked the court to quash the 2025 permission by consent, on all four grounds. The action group refused to sign. It wants a judge to rule on the issues in a reasoned judgment.
Rather than wait, the college submitted the same scheme again as a new application, 26/02109/FUL. Officers wrote a fresh report that answers each of the four grounds. The college says the second application also let the council assess the scheme against the new national planning rules published in August.
The court hearing is still on
On 29 September, Sir Peter Lane ordered that the one-day hearing stays listed for 20 October. The court will first decide whether it is appropriate to go ahead, given that the council and the college have already agreed the first permission should be quashed.
The action group asked for this week’s decision to be deferred until the court had ruled. In its amendment sheet, the council said a decision could lawfully be made with the judicial review still running.
The Master, Lord Simon McDonald, is named as the applicant. In the college’s statement he said:
“My first reaction is relief: so many people have worked so hard to secure planning permission for our Library+ project.”
He added: “The process has lasted longer than I hoped. All our opponents’ arguments have been confounded but they still have legal options. Watch this space.”
What will be built
According to the officer report, the scheme includes:
- a new library of about 1,050 square metres over four floors, with a study hub, a main reading room, group study rooms, an outdoor terrace and a “sky gallery”
- a replacement bridge to the Grade I listed Bodley Library
- changes to the college kitchen and Upper Hall, with new plant and step-free access
- relandscaping of Bath Court, the courtyard behind the library
- a temporary kitchen and dining hall in Second Court while the work goes on
The chimneys on the Christ’s Lane side would rise to about 14.6 metres and the roof parapet to about 13 metres, the report says. The modern block across the lane reaches about 15.5 metres.
The college says the 1970s library does not have enough study spaces and is not accessible enough. It also says the scheme will run on air source heat pumps, with the kitchens converted to electric.
Who objected
The report records 119 representations: 62 in support and 57 against. Cambridge Past, Present and Future also objected. The action group sent more than 70 representations of its own, plus a 75-signature petition asking for a public forum on the scheme.
Objectors’ main points, as summarised in the report:
- the building is too big for a tight site and would deepen the “canyon” along Christ’s Lane
- it would harm the Grade I listed college and the Historic Core conservation area
- the chimneys are too tall
- construction would disrupt the shops and homes on the lane
Historic England did not object. It did say the bulk of the building would cause some harm to the significance of the Grade I listed college. Officers concluded the harm to the setting of the Bodley Library is “at the lower end of the scale” and outweighed by public benefits.
What it means for you
If you use Christ’s Lane, expect works at its St Andrew’s Street end at some point, but not yet. The report says the length of the building work is “not understood to be fully known”. It says disruption is likely to centre on the junction of Christ’s Lane and St Andrew’s Street, and on Drummer Street bus station.
The college says it will now work through the planning conditions. Its first step will be the temporary kitchen and dining hall in Second Court, inside the college. Its Third Court library stays open throughout. The council notes that the decision is subject to the decision notice being issued.
The High Court hearing on 20 October could still affect the first permission. The second one cannot be issued while the government’s holding direction stands. We will report what happens on the day.
Other schemes going through the city’s planning system are on our Cambridge planning news page. The other big decision from the same meeting was the Ekin Road estate.
Have your say