Hills Avenue and Cavendish Avenue are shut to 29 November; the A14 Milton slips close nightly to 22 November. The M11 north shuts overnight on Friday 20th.
Cambridge is a small medieval city with a ring of park and ride sites around it, a bus gate in the middle of its busiest high street, and a county council that does most of its resurfacing between nine at night and five in the morning. If you drive here, three things decide your day: what is dug up, whether your route crosses Mill Road bridge, and where you are going to leave the car.
This page keeps the dated Cambridge roadworks at the top and the permanent picture underneath. Everything below comes from the county council’s own schedule, from the statutory traffic orders it advertises in the Cambridge News, and from National Highways.
What is closed right now
Hills Avenue is closed between Hills Road and Alliance Court until 29 November for gas main renewal, and Cavendish Avenue is closed too, between Hills Road and Lady Jane Court, until the same date. Cavendish Avenue is one of the two roads named as the Hills Avenue diversion, so both are shut at once until the end of the month. Baldock Way is the other road named in both diversions.
Green Street stays closed between No. 14 and Trinity Street until 4 December for building repairs.
Cowley Road closes at night, 10pm to 4am, between the Maurice Wilkes Building and Orwell House for resurfacing; the made order runs to Tuesday 17 November, so tonight should be the last night. Its cycle lane stays suspended over the same stretch until 20 November.
Three short gas closures are running this week: Church Lane between Nos. 14 and 19 until 20 November, with a signed diversion through Grantchester; Orchard Street between Nos. 5 and 7 on 17 and 18 November; and Windsor Road between Nos. 2 and 8, whose order ends today, 17 November.
East Road is finished. The county council’s resurfacing programme, re-read today, now lists it as completed. Gresham Road, Norfolk Street and Albion Row reached the end of their orders on 16 November.
These city restrictions run on:
| Street | Extent | Dates | What it is |
|---|---|---|---|
| Hills Avenue | Hills Road to Alliance Court | 9 to 29 November | Closed for gas main renewal; traffic via Baldock Way and Cavendish Avenue |
| Cavendish Avenue | Hills Road to Lady Jane Court | 16 to 29 November | Closed for gas main renewal; traffic via Baldock Way and Hills Avenue |
| Green Street | No. 14 to Trinity Street | 9 November to 4 December | Closed for building repairs, with the one-way order lifted |
| Cowley Road | Maurice Wilkes Building to Orwell House, 10pm to 4am | 13 to 17 November | Night closure for resurfacing; diversion via the A1309 and A1134 |
| Church Lane | Between Nos. 14 and 19 | 16 to 20 November | Closed for gas works, with a signed diversion through Grantchester |
| Orchard Street | Between Nos. 5 and 7 | 17 and 18 November | Closed for a new gas connection |
| Windsor Road | Between Nos. 2 and 8 | 16 and 17 November | Closed for a new gas connection |
| St Thomas's Square | St Thomas' Road to Walpole Road | 26 October to 23 December | Closed for mains repairs; diversion via Walpole Road, Birdwood Road and St Thomas' Road |
| Hills Road cycle lane | Long Road to Luard Avenue, in the words of the made order | 5 October to 4 December | Suspended for gas main replacement. Our story |
| Cowley Road cycle lane | Maurice Wilkes Building to Milton Bridge | 9 to 20 November | Suspended |
| Sidgwick Avenue | Queens Road and Silver Street junction, working hours | From 19 October, about eight weeks | Building the Greater Cambridge Partnership trial; diversion via Newnham Road, Barton Road and Grange Road. From Monday 23 November there is no through route: access from Grange Road or Queen's Road only (GCP). Our story |
| Regent Terrace | Between Nos. 19 and 30 | From 7 October until the works finish | Closed to vehicles for building demolition and safety works |
| Beaufort Place to Riverside walkway | La Mimosa to Magdalene Street, pedestrians only | 1 September to 28 February 2027 | Essential maintenance |
| Adams Road | Grange Road to Wilberforce Road, both kerbs | Permanent, from 17 September 2026 | New no waiting at any time restrictions in 14 marked lengths |
| Gurney Way | Outside No. 18 | Permanent, from 15 October 2026 | 6 metres of residents' parking bay removed for a new dropped kerb |
The Hills Avenue, Cavendish Avenue, Cowley Road, Church Lane, Orchard Street, Windsor Road, Green Street and St Thomas’s Square dates are from the county council’s made orders of 28 October; we re-read the Cambridge closures order today. East Road’s completion is from the council’s own road improvements programme, re-read on 17 November. The Regent Terrace order came into operation on 7 October. It runs until the works are finished, with a legal maximum that ends in February 2028, and the notice gives no expected finish date. The Adams Road order is not roadworks: it came into operation on 17 September, putting double yellow lines along most of both kerbs between Grange Road and Wilberforce Road. The Gurney Way order was made on 7 October and came into operation on 15 October.
National Highways closures near Cambridge to Sunday 22 November
National Highways’ seven day closure report, last updated on Monday 16 November, runs to Sunday 22 November. These are the entries that affect Cambridge drivers. All of them are overnight.
- Every night to Sunday 22 November, 8pm to 6am: the A14 eastbound exit slip at junction 33 Milton and the westbound entry slip at junction 33 are closed, for communications work. The previous report stopped these on Thursday; the new one runs them through the weekend.
- Thursday 19 November, 9pm to 5am: the M11 southbound exit slip at junction 11 Trumpington is closed, also for communications work.
- Friday 20 November, 9pm to 5am: the M11 northbound is fully closed between junction 11 Trumpington and junction 14 Girton, for drainage work.
- Saturday 21 and Sunday 22 November, 8pm to 6am: the A428 is closed in both directions between North Farm and Toseland, for anti-skid surfacing.
- Tuesday 17 November, 8pm to 6am: the A14 westbound is fully closed between junctions 24 and 21, with the junction 23 westbound entry slip shut, for carriageway reconstruction.
- Wednesday 18 and Thursday 19 November, 8pm to 6am: the same work moves to the A14 eastbound between junctions 21 and 24, and the A1 southbound link to the A14 eastbound closes.
- Tuesday 17 to Friday 20 November, 9pm to 5am: Brampton Hut roundabout on the A14 near Huntingdon is partly closed, and the A1 northbound exit slip there is shut, for drainage.
- Thursday 19 and Friday 20 November, 9pm to 5am: the A1 northbound is closed between Tempsford and the Black Cat roundabout, for the A1 and A421 bypass construction.
The report lists no weekend closure of the A14 near Cambridge up to 22 November, and no closure of the A14 between Girton and Stow-cum-Quy apart from the Milton slips.
The A14 at Milton: the four-month order is in force
A National Highways order for the A14 between junction 33 Milton and junction 35 Stow-cum-Quy came into force on 24 August 2026. It covers resurfacing, waterproofing, bridge expansion joints, drainage, safety barriers and road markings, with the work expected to last about four months. It allows, 24 hours a day and with narrow lanes:
- 50mph eastbound for 950 metres from just east of the junction 33 overbridge, westbound for 1,500 metres from the junction 35 entry slip, and on the junction 33 eastbound entry slip
- 40mph on the stretches between those, eastbound up to the junction 34 Fen Ditton exit slip and westbound to just past the junction 34 entry slip
- closure of every layby between junctions 33 and 35
The notice is clear that the limits apply only where traffic signs show them. The closure report for 29 October to 4 November describes the three eastbound full closures from 2 November as structure maintenance, which fits the bridge joint work in the order. The order is legally in force, but we could not confirm today that the 50mph and 40mph signs are up.
The proposed A14 weekend closures still have not started
National Highways gave notice on 3 September that it intended to make an order for drainage and resurfacing on the A14 west of the city, with full weekend closures, 8pm Friday to 6am Monday, starting on or after Friday 18 September and lasting about two months. The signed diversion would run via Brampton Hut, the A1 and the A428, rejoining the A14 at Girton.
Nine weekends have now passed without one. The closure report updated on 16 November, running to 22 November, lists no weekend closure of the A14 near Cambridge. It does list overnight closures between junctions 24 and 21 for carriageway reconstruction from 16 to 19 November, but the report does not say whether those belong to the same scheme, and we found no notice saying the weekend order has been made. Treat the weekend closures as an advertised intention until National Highways lists a dated one.
Starting in the next fortnight
These closures are all from the county council’s made orders published on 28 October, so the dates are the council’s decision rather than its intention. They still move if the works themselves move. When we checked on 14 November we found no newer batch of Cambridge orders on the Public Notice Portal. Its listing pages would not load for us today, so we cannot confirm that no new batch has appeared since; we will add any we find.
| Road | Dates | What happens |
|---|---|---|
| Fen Road | Sunday 22 November, 12.20am to 8.30am | Closed 20 metres either side of the level crossing for maintenance |
| Suez Road | 23 and 24 November | Closed from Mill Road to No. 8a for a new gas connection |
| Peas Hill | 23 November 2026 to 22 May 2028 | Closed between No. 1 and Bene't Street, with no waiting, for scaffolding and crane lifts on the theatre redevelopment |
The same batch carries a surface treatment order from 1 November covering more than 50 city streets, among them Mill Road side streets such as Cavendish Road, Cyprus Road, Malta Road, Madras Road and Hobart Road, plus Campkin Road, De Freville Avenue, Harvey Road and Richmond Road. It gives a window to April 2028 for each road, not a date, so it does not mean any of them shuts on 1 November.
The resurfacing programme has moved since our last check. Two city roads are still down for autumn 2026 with no firm dates: Madingley Road between Northampton Street and Storeys Way, and Barton Road from Newnham Road towards Grantchester Road. Marlowe Road now has a date, 6 January 2027, closed for three days, 8am to 6pm. Newmarket Road, from Wadloes Road to Meadowlands Road and either side of De Bruyne Street, has slipped to spring 2027, and Hills Road is scheduled for summer 2027 in three sections: Long Road to Cherry Hinton Road, Cherry Hinton Road to Station Road, and Station Road to St Paul’s Walk.
The council warns that dates move at short notice. Its own live map is the one.network service, which now asks anonymous visitors to sign in before it shows a roadworks list, so it is less useful than it was.
Trains: no King’s Cross trains on 28 and 29 November
The big one is the last weekend of the month. No trains run between King’s Cross and Letchworth Garden City or Peterborough on Saturday 28 and Sunday 29 November, until 6.40am on Monday 30 November, for digital signalling and track work. Shuttle trains run between Letchworth and Cambridge, and tickets are accepted on Greater Anglia between Liverpool Street and Cambridge North. Our story has the detail.
Before then:
- Sunday 22 November, early morning: on Great Northern and Thameslink, buses replace trains between Finsbury Park and Welwyn Garden City or Stevenage from 12.30am to 5.45am, between Welwyn Garden City and Stevenage or Letchworth from 2am to 7.55am, and between Stevenage and Peterborough from 2am to 9.30am. No trains run between Finsbury Park and King’s Cross before 7.15am.
- Monday 23 to Friday 27 November, 11.35pm to 5.15am: Greater Anglia trains that normally run via Seven Sisters, including those to Cambridge North, go via Tottenham Hale instead, with slightly longer journeys.
All of these are on National Rail’s own engineering notices, re-read on 17 November. Use the National Rail journey planner before you travel.
Journey times and fares on the London route are on Cambridge to London trains.
The Mill Road bus gate
If you take one thing from this page, take this. Mill Road bridge is a bus gate. Driving a non-exempt vehicle over it gets you a £70 penalty charge notice, reduced to £35 if you pay within 21 days and increased by 50% to £105 if you neither pay nor challenge within 28 days. Enforcement is by ANPR camera and began on 11 March 2025.
Exempt vehicles are buses, taxis, emergency services, vehicles in the disabled tax class, registered Blue Badge holders’ vehicles and anything on the council’s permitted vehicle list. Registration is not automatic: Blue Badge holders must register up to two vehicles through the council’s MiPermit portal, and disabled residents who are not Blue Badge holders, plus their carers and professional carers doing home visits in the Mill Road area, can apply separately. An exemption for Mill Road does not cover any other bus gate or bus lane in Cambridge, and there are plenty: Regent Street, Emmanuel Road, Bridge Street, Station Road, Silver Street and Worts Causeway all have one, and four bus lanes are enforced on Elizabeth Way, Newmarket Road in both directions and Hills Road inbound.
The restriction is not under review in the short term. The council has said the Highways and Transport Committee will receive its report on the bus gate in spring 2027, two years after enforcement began.
Park and ride, and what it saves you
Cambridge has five park and ride sites on the approaches to the city: Madingley Road (route PR1, CB3 0EX), Newmarket Road (PR2, CB5 8AA), Trumpington (PR3, CB2 9FT), Babraham Road (PR4, CB22 3AB) and Milton (CB24 6DQ).
Parking is free for up to 18 hours. Beyond that it is £10 for 18 to 24 hours, £20 for 24 to 48 hours and £30 for 48 to 72 hours, paid through RingGo within the first hour of arrival. The bus fares are:
- Adult return £4.50, with up to four under-5s free with each fare-paying adult
- Child return £1 for ages 5 to 15 with a fare-paying adult or a Tiger Pass, up to four children per adult
- Short hop return £3.80, between Babraham Road and Addenbrooke’s, and between Newmarket Road and the Abbey Stadium on match days
- Small group £10 for up to three people, large group £15 for up to five, both giving a day’s travel in the Cambridge town zone
Both group tickets have gone up by 50p and £1 since the summer. The season tickets are back on the site, after a spell when it listed none: a week on park and ride buses only is £14, a week on park and ride and Stagecoach buses across Cambridge is £15, and the monthly Megarider Xtra is £57.60 on automatic payment. A single is £3, and return tickets are only valid on the day you buy them, so an overnight stay means two singles.
Concessionary pass holders with a Cambridgeshire and Peterborough Combined Authority pass travel free all day; other English National Concessionary passes are valid after 09:30 on weekdays and all day at weekends.
There is one thing to know about Babraham Road. A Public Space Protection Order came into force there on 30 July 2026 after a joint consultation by the city and district councils, in which 88% of 160-plus respondents backed tougher measures against dangerous and disruptive driving at the site. Breaches are now finable and enforcement is by ANPR and CCTV without staff on site. Milton park and ride has had a similar order since last year.
City centre car parks
Cambridge City Council runs five multi-storey car parks: Grand Arcade, Park Street, Grafton East, Grafton West and Queen Anne Terrace. All are short-stay, all take cash, card, Apple Pay and Android Pay, and all give Blue Badge holders three hours free if you scan the badge when you pay.
Castle Hill car park is back. The council shut it from 10 to 23 September for electrical maintenance, and its alerts page now lists that closure as resolved. Castle Hill is the cheapest all-day parking in the city at £10 for over four hours; the background is in Castle Hill car park closed 10 to 23 September.
| Car park | 1 hour, weekday | Longest band, weekday | Longest band, weekend | Spaces |
|---|---|---|---|---|
| Grand Arcade, CB2 3QF | £3.70 | £33.50 over 5 hours | £36.50 over 5 hours | 951 |
| Park Street, CB5 8AS | £3.70 | £33.50 over 5 hours | £36.50 over 5 hours | 222 |
| Grafton East, CB1 1PS | £3.10 | £30.60 over 5 hours | £33.70 over 5 hours | 412 |
| Queen Anne Terrace, CB1 1ND | £2.60 | £24.00 over 6 hours | £26.00 over 6 hours | 572 |
Queen Anne Terrace is the cheapest for a long stay and the council says so on its own page. It also has 40 electric vehicle charging points, free motorcycle parking on the ground floor and a 2.1 metre height limit, against 1.98 metres at the other two. It is about a 15-minute walk from the centre, and it is the obvious choice for Parker’s Piece, the Grafton, Anglia Ruskin and Parkside pool. Its lift is working again, after a spell out of service over the summer: the council now gives its hours as 8am to 8pm Monday to Saturday and 10am to 5pm on Sunday. Parking there is free from 6pm until the next daytime tariff.
Grand Arcade is the closest to the colleges and the river and is priced accordingly. The lift fault is fixed. The council’s alerts page now lists its 28 September lower-level lift alert as resolved, and the car park page says the lift runs 24 hours a day. The Changing Places toilet there is still closed for repairs, and the council points people to the one on Drummer Street. Coaches are not allowed at any of the three; the council directs them to Madingley Road park and ride.
Evening and overnight parking, from 6pm until the next daytime tariff, is £1.80 an hour at the Grand Arcade and £1.30 at Grafton East.
Frequently asked questions
What roads are closed in Cambridge right now?
Hills Avenue and Cavendish Avenue are both closed to 29 November for gas main renewal. Green Street is closed to 4 December, St Thomas’s Square to 23 December and Church Lane to 20 November. Cowley Road closes at night, 10pm to 4am, with 17 November the last date in its order. The Hills Road cycle lane is suspended to 4 December and Regent Terrace is closed between Nos. 19 and 30. On the trunk roads, the A14 slip roads at junction 33 Milton close every night to Sunday 22 November, and the M11 northbound is shut between junctions 11 and 14 overnight on Friday 20 November.
When is the Hills Road cycle lane closed?
The west side cycle lane on Hills Road, from Long Road to Luard Avenue in the made order, is suspended from 5 October to 4 December 2026 for gas main replacement. The county council published the made order on 23 September. The suspension applies while the signs are up at each end of the works.
Is the A14 closed at weekends now?
No. National Highways advertised an order on 3 September proposing full weekend closures of the A14 west of Huntingdon from 18 September, but no weekend closure appears in its closure report updated on 16 November, which runs to 22 November, and we found no notice saying the order has been made. Near Cambridge that report lists only overnight closures of the junction 33 Milton slip roads, every night to 22 November.
Is the A14 at Milton down to 50mph?
The order allowing it is in force. National Highways made it with effect from 24 August, for about four months of resurfacing and bridge work between junction 33 and junction 35. It permits 50mph and 40mph limits with narrow lanes, but only where signs show them, and we could not confirm today that they are up.
How much is the Mill Road bus gate fine?
£70, reduced to £35 if you pay within 21 days, and increased to £105 if you do not pay or challenge within 28 days. Enforcement is by ANPR camera and started on 11 March 2025.
Is Cambridge park and ride free?
Parking is free for up to 18 hours; you pay for the bus. An adult return is £4.50 and a child return is £1 with a fare-paying adult. A week on the park and ride buses is £14, or £15 including Stagecoach buses across the city. Staying longer than 18 hours costs £10 up to 24 hours, £20 up to 48 and £30 up to 72.
Which Cambridge car park is cheapest?
For a full day, Castle Hill off Castle Street, at £10 for over four hours on a weekday and a flat £5 on a Sunday. Its 10 to 23 September maintenance closure is over. Of the multi-storeys, Queen Anne Terrace on Gonville Place is cheapest at £24 for over six hours on a weekday and £26 at the weekend, against £33.50 and £36.50 at the Grand Arcade and Park Street. Queen Anne Terrace is also free after 6pm.
Sources
- Cambridgeshire County Council, road improvements programme for the Cambridge city resurfacing schedule, start dates, durations and working hours.
- National Highways seven day closure report, the spreadsheet edition updated 16 November 2026 and covering 16 to 22 November, for the A14, M11, A428, A1 and Brampton Hut overnight closures.
- National Highways notices for the A14 junction 33 to junction 35 order: advertised 6 August 2026 and made, published 20 August 2026, for the start date, speed limits and layby closures.
- National Highways notice for the A1 and A14 order, 3 September 2026 for the proposed weekend closures from 18 September and the A428 diversion.
- Cambridgeshire County Council’s made temporary traffic orders, Cambridge batch published 23 September 2026 and Cambridgeshire batch published 23 September 2026, for Hills Road, Regent Terrace and the late October closures, re-read on 27 October.
- Cambridgeshire County Council’s made temporary traffic orders, Cambridgeshire batch published 28 October 2026 and Cambridge road closures published 28 October 2026, for James Street, Albion Row, Kings Hedges Road, Arbury Road, Hills Avenue, Green Street, the cycle lane suspensions, the 1 November surface treatment order and the later November closures including Peas Hill, Fen Road, Suez Road, Orchard Street, Church Lane and Windsor Road. These replace the proposed versions published on 21 October.
- Statutory temporary traffic orders advertised by Cambridgeshire County Council: the notices published 16 September 2026 and 16 September 2026 for the October batch and Fen Road; and the notices of 26 August 2026 and 19 August 2026 for the earlier city closures.
- Cambridgeshire County Council waiting restrictions notice, published 16 September 2026 for the Adams Road order made on 11 September and in operation from 17 September, and for the Milton Road residents’ parking amendment and its 7 October deadline.
- National Rail engineering notices for King’s Cross to Peterborough, 28 to 30 November, Seven Sisters line nights, 23 to 27 November, Finsbury Park and King’s Cross, 22 November and Finsbury Park and Hitchin to Peterborough, 21 and 22 November.
- Cambridgeshire County Council, Mill Road bridge TRO and bus lane and bus gate enforcement for the £70 charge, the discount and surcharge, the 11 March 2025 start, the exemptions, the list of gates and lanes and the spring 2027 committee report.
- Cambridge Park and Ride pricing for parking charges, bus fares, the weekly and monthly passes and the single fare, and the site pages for locations and route numbers.
- Cambridge City Council, Grand Arcade, Park Street, Grafton East, Queen Anne Terrace and Castle Hill car park pages for tariffs, capacities, height limits and lift status, the council’s alerts page, which lists the Castle Hill closure and its 28 September Grand Arcade lift alert as resolved.
- Cambridge City Council, Castle Hill car park closed from 10 to 23 September, published 3 September 2026.
- Cambridge City Council, crackdown on anti-social driving at Babraham Road Park and Ride, 30 July 2026 for the Public Space Protection Order.
Checked 17 November 2026. Re-read today: the National Highways closure report (16 to 22 November), the county resurfacing programme, the county’s made Cambridge closures order of 28 October, the National Rail engineering notices listed above and the city council’s alerts page, which shows no current alerts. A search of the Greater Cambridge Partnership’s Sidgwick Avenue pages found no update since the works began on 19 October. The Public Notice Portal’s listing pages would not load today, so we could not confirm whether a newer batch of Cambridge orders has been published since 14 November. The Beaufort Place details, Queen Anne Terrace lift and opening details, park and ride prices and car park tariffs were not re-read today and carry forward from earlier checks between 11 September and 24 October. We did not try Greater Anglia’s or Great Northern’s own engineering pages, which have refused the connection on earlier checks, so train details rest on National Rail. Roadworks dates move at short notice and tariffs change each year, so confirm against the council’s own pages before you set off. Trains instead of the car are covered on Cambridge to London trains; what is being built is on Cambridge planning.