Councillors voted 40 to 8 to seek government powers for a 6.5km busway from Waterbeach New Town to north Cambridge. Buses would not run before 2031.

Cambridgeshire County Council has voted to ask the government for the powers to build a busway between Waterbeach New Town and north Cambridge. The vote at Full Council on Tuesday 13 October was 40 in favour and 8 against, with 7 abstentions.

That is not planning permission. The council is applying for a Transport and Works Act Order, and the Transport Secretary makes the final decision. The council’s report expects the application to go in next month. Buses would not run on the route until mid to late 2031.

Waterbeach is about six miles north of Cambridge city centre. Most of the route runs through South Cambridgeshire, but it would feed buses into the city on the existing guided busway.

The decision is item 7 on the meeting page for Full Council on 13 October, where the report and the recorded vote are both published.

What would be built

The report to councillors describes a guided busway of about 6.5km. It would run between the new town at Waterbeach and north Cambridge, via Landbeach and Milton Park and Ride.

The scheme includes:

  • a guided busway, joining the existing Cambridgeshire Guided Busway just west of where that busway passes under the A14
  • a widened Milton Road/Butt Lane, where buses would run on the road towards Milton Park and Ride
  • a remodelled entrance at Milton Park and Ride, so guided buses can call there
  • stops at Butt Lane, at Landbeach Road south of Landbeach, and at Waterbeach Road
  • a travel hub for up to 1,600 vehicles, west of the A10 opposite Waterbeach New Town
  • a walking and cycling path along the busway’s maintenance track

A new roundabout on the A10 would serve both the travel hub and the southern entrance to the new town. The developer, Urban & Civic, will build it and share the cost with the busway scheme. From there, buses would join the roads through the new town towards the proposed new railway station.

The report says the council’s preference is a sensor-guided system using electric or hybrid buses, rather than the concrete kerbs on the existing busway. Trials are still going on.

Why the council voted a second time

Councillors first agreed to apply in February 2025. The report says an application would normally follow within about six months. It is now expected in November 2026, some 21 months later.

The report gives three reasons for the delay:

  • the Environment Agency revised its flood mapping in March 2025, forcing a redesign of the flood compensation and drainage
  • groundwater readings over the winter of 2026 were much higher than expected, so the ponds and water storage at the travel hub had to be redesigned
  • the A10 roundabout did not get planning permission until June 2026, against an expected autumn 2025

The council’s lawyers advised a fresh resolution to cover changes to the land needed and to reduce the risk of a challenge. A new national rule since February 2026 also means the council no longer has to hold a second confirming vote after the application is made.

How councillors voted

The law requires a majority of the whole council, not just of those in the room. The recorded vote shows 40 of the council’s 61 members voted yes.

Group Yes No Abstained
Liberal Democrat and Independent (33 members) 30 0 0
Conservative (12) 3 6 0
Reform UK (8) 2 0 6
Labour (5) 5 0 0
Green (2) 0 2 0
Non-aligned independent (1) 0 0 1
Total 40 8 7

The rest of the 61 members did not vote.

When it would open

Timeline of the Waterbeach to Cambridge busway: first council resolution February 2025; Full Council votes 40 to 8 with 7 abstentions on 13 October 2026; application expected November 2026; public inquiry likely mid 2027; government decision and order in force late 2027 to mid 2028; detailed design and Full Business Case mid 2029; construction starts late 2029; planned opening mid to late 2031.
Key dates from the county council's report. Graphic by Cambridge Local News
Share this chartFacebookWhatsAppX

The report’s programme assumes people will object. If they do, a public inquiry is likely in mid 2027. The report gives two estimates for the outcome. One says the order would come into force early in 2028. Its programme table says statutory approval in mid 2028.

After that:

  • detailed design would be finished by mid 2029
  • a Full Business Case would then decide whether to fund construction
  • building would start in late 2029
  • the busway would open in mid to late 2031

Who pays

The report says applying commits the council to nothing on construction. That needs a Full Business Case, not expected until the second half of 2029.

Delivery is expected to be paid for through the Greater Cambridge City Deal and developer contributions. The council’s finance director warns the scheme “may require interim financing arrangements” before all of that money arrives. A decision to build will need confirmation that the scheme is affordable at that time.

Buying the land is estimated at no more than £3.5 million, paid from City Deal funds. The report puts the scheme’s benefit to cost ratio at 1.4, on conventional transport measures.

The report also notes that local government reorganisation could change who finishes the job. A successor council may be in place by the time the government decides.

What it means for you

  • If you commute from Waterbeach, Landbeach or Milton: nothing changes for about five years. The earliest planned opening is mid 2031.
  • If you use Milton Park and Ride: guided buses would call there, and its entrance and Butt Lane would be rebuilt.
  • If you own or rent land on the route: the council is seeking compulsory purchase powers, as well as temporary use of land for building and for five years after opening. The report says negotiations with landowners are going on. Anyone affected is entitled to compensation, and disputes go to the Upper Tribunal (Lands Chamber).
  • If you want to object: objections go to the Transport Secretary once the application is made. Objections from people whose land is to be taken lead to a public inquiry or hearing. We will say when the application goes in.

The Greater Cambridge Partnership’s project page carries the scheme’s background and consultation history. The government approved the Cambourne to Cambridge busway in September after the same process. For what is shut on the roads this week, see our roadworks and travel page.