Brackley Close and Rutland Close flats join the Kingsway rebuild, so 223 households will be asked to move. Applications to move open on 26 October.
Another 48 council properties in north Cambridge are to be knocked down and rebuilt. Cambridge City Council’s Cabinet has added 2 to 48 Brackley Close and 2 to 48 Rutland Close (even numbers) to its Kingsway redevelopment.
With the extra blocks, 223 households across the Arbury Court and Kingsway sites will be asked to leave their homes. Anyone who wants to go early can apply to move from Monday 26 October.
Updated 30 October: the decision was not called in and took effect on 28 October. The consultation is now open until Friday 20 November, and the dates below are confirmed.
The decision was taken at Cabinet on Tuesday 20 October and published the next day. It can still be called in by councillors until 27 October. If it is not, it takes effect on 28 October.
What changes
The Cabinet report sets out what the bigger scheme means:
- Homes: 487 in total instead of 410. Current designs show 287 at Kingsway and 200 at Arbury Court.
- Council homes: up from 206 to 245, with at least half of the homes across the two sites to be council homes.
- Budget: up from £81.2 million to £103.2 million.
- Arbury Court: 12 commercial units, a library and “affordable workspace” for local charities, plus changes to the park and civic space.
- Kingsway: a large new open space where the extra blocks stand now, according to early designs by the architects PRP.
The report gives the new council home total as 245 in its recommendations and 244 in the background section.
Of the £103.2 million, £65.3 million is the cost of the housing itself. Moving residents out, known as decant costs, accounts for £23.7 million. Replacing the library and shops takes £8.1 million, and other fees £6.1 million.
Why the two closes were added
The council asked tenants and leaseholders in the two closes in July whether their homes needed redeveloping. Officers knocked on doors twice and held two drop-in sessions at Meadows Community Centre.
According to the report, 69% of households replied. Of those, 79% were in favour of redevelopment, 11% were against and 10% were unsure.
Residents described homes that were too hot in summer (57%) and damp or mouldy (50%). Some 45% said their home was too cold in winter, and 32.5% raised anti-social behaviour or personal safety.
When people will have to move
The council had told residents they could first apply to move once a planning application for Arbury Court went in. It has now brought that forward.
The report says the £96.3 million Homes England partnership gives it enough certainty to let people start now. The council says it has written to all residents in the existing scheme to confirm they can apply from 26 October. Residents of the two newly added closes can also apply from that date.
What residents are offered:
- Council tenants: emergency banding on the housing register.
- Leaseholders and freeholders: the council will buy their homes under its regeneration policy.
- Payments: Home Loss and Disturbance payments for qualifying tenants, and Home Loss, Basic Loss and Disturbance payments for qualifying owners.
Nobody who prefers to stay longer will be expected to move before summer 2028. The council expects the whole process to take several years.
Moves will be prioritised by:
- which estate is due to start building first
- the applicant’s Home-Link priority date
- inspected damp, condensation and mould, judged by severity and by the age and vulnerability of the household. These cases can jump the first two.
Cabinet also gave officers power to make a compulsory purchase order for leasehold flats at Kingsway, Brackley Close and Arbury Court, and for five freehold homes on Rutland Close and Verulam Way. That applies only if the homes cannot be bought by agreement within a reasonable time and cost.
Davy Road gets more social rent homes
The same report increases the council’s planned Davy Road redevelopment from 45 to 57 council homes. Social rent homes rise from 5 to 34. The budget goes from £17.8 million to £20.3 million.
A planning application is due this autumn. If it is approved, the council expects building to start by summer 2028.
What it means for you
If you live at Arbury Court, Kingsway, Brackley Close, Rutland Close or Verulam Way, you can ask the council’s rehousing team about moving from 26 October. You do not have to move yet if you do not want to.
The next round of public consultation on the designs opened on 28 October, run by Cambridge Investment Partnership, the council’s joint venture with The Hill Group. The council’s announcement confirms these dates. You can see the plans and fill in the surveys on the Shaping north Cambridge page, or pick up printed copies at Arbury Court Library and The Meadows Community Centre.
| What | When | Where |
|---|---|---|
| Survey opens | Wednesday 28 October | Online |
| Arbury Court consultation | Wednesday 28 October, 4pm to 7pm | Church of the Good Shepherd |
| Kingsway consultation | Wednesday 4 November, 4pm to 7pm | Church of the Good Shepherd |
| Arbury Court drop-in | Saturday 7 November, 11am to 1pm | Meadows Community Centre |
| Kingsway drop-in | Saturday 7 November, 1.30pm to 3.30pm | Meadows Community Centre |
| Arbury Court webinar | Thursday 12 November, 5.30pm to 6.30pm | Online |
| Kingsway webinar | Thursday 19 November, 5.30pm to 6.30pm | Online |
| Survey closes | Friday 20 November |
A further consultation follows in early 2027. The council now says planning applications for both sites are expected later in 2027. When they go in, they will appear on the Greater Cambridge register, and our Cambridge planning news page tracks the big ones.
Have your say